First CoilHose operation in Malaysia
Objectives
  • Expro under its multi service contract had been requested to mobilise conventional coil tubing as a contingency to lift the overbalance cushion in a newly completed well
  • Operations were planned to be conducted on the critical path with the use of a drilling rig
  • Incumbent supplier was not able to provide a coil tubing package within the requested time frame and therefore posed a potential delay to the work scope which would impact delivery of the entire project
  • Coil Tubing is used as a key contingency should the well be unable to flow naturally and is therefore imperative to the overall operation
Expro Excellence
  • Expro provided a proposed engineered solution with its latest 3/4" OD CoilHose Light Well Circulation System
  • Equipment was prepared and mobilised to the region within 21 days where a successful Site Integration Test (SIT) was completed prior to mobilisation to the rig
  • Key interfaces with the rig and other key suppliers were successfully managed
  • Expro delivery met the customer expectations and the project continued without delay
Value to client
  • Overall delivery of the well without impacting the project timeline
  • Equipment was mobilised on a scheduled vessel with other rig supplies which removed the requirement for a chartered vessel that would normally be required for conventional coil tubing
  • Reduced package footprint allowed for an optimum rig up that was prepared offline ahead of the operational requirements
  • Operational rig up, rig down timings were vastly improved and were performed with a multi-disciplined reduced POB
  • First ever well to be successfully unloaded using CoilHose technology in the Asia Pacific region
Contact

First CoilHose operation in Malaysia

In Brief
Expro delivers first CoilHose operation in Malaysia to support well test operation
Product Line
Well Intervention
Region
Asia, Middle East And North Africa
Objectives
  • Expro under its multi service contract had been requested to mobilise conventional coil tubing as a contingency to lift the overbalance cushion in a newly completed well
  • Operations were planned to be conducted on the critical path with the use of a drilling rig
  • Incumbent supplier was not able to provide a coil tubing package within the requested time frame and therefore posed a potential delay to the work scope which would impact delivery of the entire project
  • Coil Tubing is used as a key contingency should the well be unable to flow naturally and is therefore imperative to the overall operation
Expro Excellence
  • Expro provided a proposed engineered solution with its latest 3/4" OD CoilHose Light Well Circulation System
  • Equipment was prepared and mobilised to the region within 21 days where a successful Site Integration Test (SIT) was completed prior to mobilisation to the rig
  • Key interfaces with the rig and other key suppliers were successfully managed
  • Expro delivery met the customer expectations and the project continued without delay
Value to client
  • Overall delivery of the well without impacting the project timeline
  • Equipment was mobilised on a scheduled vessel with other rig supplies which removed the requirement for a chartered vessel that would normally be required for conventional coil tubing
  • Reduced package footprint allowed for an optimum rig up that was prepared offline ahead of the operational requirements
  • Operational rig up, rig down timings were vastly improved and were performed with a multi-disciplined reduced POB
  • First ever well to be successfully unloaded using CoilHose technology in the Asia Pacific region